NEBRASKA CITY – Construction and facility Manager Marty Stovall reports additional closures on 11th Street ahead.

Constructors Inc. will close 11th Street from the south side of the First Corso intersection to the north side of Fourth Corso.

The schedule for the north side of the project includes removal of communications poles and pavement, as well as the start of sewer work. Paving is expected to start in early August.

The south side of the project, which includes Fourth to Seventh Corso is expected to open to traffic at the end of July.

Stovall said work on the Fourth Corso intersection will be phased so that it is always open for east and west traffic.