Falls City to restrict alley access during three-week electrical construction

FALLS CITY – Falls City is announcing the next phase of its electrical distribution improvements, which includes construction in downtown alleys.
Watts Electric is expected to make contact with residents about locating sewer lines and other utilities in areas where underground electrical equipment is planned. Alley access will be restricted for two to three weeks.
Watts Electric is scheduled to begin working Monday on alleys between Chase and Stone streets from 11th to 13th Streets.
Project Details:
- Who: Watts Electric
- What: Installing underground electric lines to eliminate overhead power.
- Notice: Limited to zero alley access during construction
- When: Approximate target dates (subject to change)
7/15/24 to 08/02/24: Alleys from 11th to 13th Streets, Between Chase & Stone Streets
8/15/24 to 08/23/24: Alleys from 11th to 13th Streets, Between Stone & Harlan Streets
08/26/24 to 09/06/24: Alleys from 13th to 14th Streets, Between Stone & Harlan Streets